Designing The Modular Regional Airport: Vertiports, Data Centres And Room To Grow

Writer: Gebler Tooth Architects
Gebler Tooth Architects
4 days ago
7 min read


Regional airports rarely get to plan for one future. Passenger numbers may grow or stall. Electric air taxis could arrive towards the end of the decade, or later. Data centre developers are looking for land and power, and other uses may follow. Each opportunity has its own timescale, and none comes with a guarantee.


That uncertainty is why modularisation deserves a central place in airport design. Instead of one large, fixed project, a modular approach treats the estate as a set of defined, repeatable parts: building bays, plant blocks, data halls, pads and plots. Each can be designed once, delivered when it is needed and added to without starting again. For a regional airport, that means investment can follow demand while the estate stays ready for opportunities that have not yet arrived.


This post sets out the approach first, then tests it against two of the most likely new demands: vertiports and data centres.


What Modularisation Means For An Airport


Modularisation organises a development into defined elements that can be designed, procured and delivered in stages. Standardisation repeats dimensions, components and interfaces where requirements are similar enough. For an airport, the idea works at three scales.


  • Components -  Repeatable structural bays, façade panels, washrooms and plant assemblies, manufactured off-site where that makes sense. With enough repetition, consistent procurement and scale, later phases can become quicker and more predictable to deliver, though those savings are not automatic.


  • Buildings - A terminal or passenger building that grows bay by bay, and a data centre that grows hall by hall, each designed so the next module can follow without remodelling the last.


  • The estate - Plots with defined footprints, height limits, access and reserved utility routes, so each new use has a place to connect.


Modular does not have to mean a building delivered as prefabricated boxes, and most modules are not designed to be lifted out and swapped.


Nor does every facility need the same grid: terminals, pads and data halls can keep the structural grid that suits them, as long as their setting-out, levels and interfaces are coordinated.


The estate scale is where modularisation does most for a regional airport. We think of it as a masterplan with sockets.



Phase one builds the first bay, pad and hall. Dashed elements are safeguarded land and reserved routes, not installed infrastructure: connections follow when each phase is confirmed. A future module can connect only where capacity and technical compatibility have been designed in, so the corridor reserves space for power, data, water and drainage, with ducts installed ahead of demand only where the business case supports it.


Keeping Alternative Opportunities Open


Modularisation also protects the options nobody has asked for yet. A reserved plot can keep more than one future open, such as a second pad, a data hall, a hotel or a logistics building. Each needs different access, servicing, safeguarding and planning, so every option should be tested before it is promised.


The same thinking applies to buildings. A modular passenger facility can open a new route quickly, and later be extended, relocated or replaced. That is practical only if foundations, connections, access and the cost of moving were planned from the start. Standard components also keep paying off after handover: consistent doors, façade panels, fittings and plant layouts mean fewer spare parts and simpler maintenance, provided structure, architecture and services agree their dimensions and connections before manufacture.


Where The Modules Meet


Every module on the estate, whether a terminal extension, a vertiport or a data hall, draws on the same things: land near the airfield, utility routes, grid capacity and airport services. Planned separately, they compete for them. Planned as modules of one estate, they can share what makes sense and stay apart where they must.



The masterplan should set out what is coordinated, what is potentially shared and what stays separate. Utility corridors, substation land and the coordinated BIM model can be planned once for the whole estate. A grid connection, rescue and firefighting cover and car parks may be shared after capacity checks. Critical systems stay with each module: a data centre's resilience must meet its operator's requirements, which usually differ greatly from those of a passenger building.


Two opportunities sit at this junction, and both need feasibility work. A shared energy hub, with solar, battery storage and an upgraded grid connection, could serve the data centre, eVTOL charging and electric ground vehicles. Waste heat from a data centre could warm terminals, hangars or nearby buildings where distance, temperature and demand make it viable; at Blackpool Airport, the Silicon Sands data centre concession includes connecting data centre heat to a proposed local heat network.


A coordinated BIM model helps test each new module against existing buildings, service routes and safeguarding before anything reaches site. It becomes a reliable digital twin only if it is kept up to date with records of what was actually installed.


Building In Steps


A modular estate does not need to grow in a fixed order. Terminal, vertiport and data centre investment can move at different speeds, each starting when its own gate is met.



Those gates should be real commercial and regulatory triggers: the necessary approvals, an operator commitment, a signed tenant, confirmed utility capacity or sustained growth in demand. That ties every phase to a business case, not a guess.


A few pitfalls can undo the approach:


  • Standardising too early, before aircraft or tenant requirements are understood.

  • Reserving land that cannot be reached, with no route for services or construction traffic.

  • Phases that only work when finished. Each should operate safely on its own.

  • Lock-in to one supplier. Open interfaces and equivalent products keep later phases flexible.

  • Forgetting the live airport. Off-site manufacture cuts site work, but not cranes, deliveries or foundations.


Two demands show how this works in practice: vertiports and data centres. They look very different, but both suit modular design for the same reason: their size and timing are uncertain.


Vertiports: Modular Design For Moving Rules



The uncertainty here is regulatory. The CAA's eVTOL Delivery Model sets an ambition to have regulatory frameworks and operational systems in place by the end of 2028 that allow initial commercial passenger flights. That is a target for readiness, not a start date for services, and the CAA says the aerodrome frameworks are not yet in place. Its 2024 design proposals for vertiports at existing aerodromes are based on heliport principles and expected to evolve into a performance-based standard that may change the required dimensions.


A modular approach handles this by separating what can be fixed now from what should stay open. Early UK schemes show both sides. Urban-Air Port's Air-One in Coventry was a temporary, prefabricated demonstrator, opened in April 2022 and designed for rapid assembly and disassembly. It proved that modular ground infrastructure can go up quickly, not how permanent airport facilities should be built. Skyports' Bicester vertiport, operationally complete in mid-2025 as a facility for flight tests and demonstrations, was designed to develop with evolving eVTOL technologies.


For a regional airport, that suggests a phased vertiport:


  1. Standardise the passenger building. Structural bays, façade panels and washrooms can repeat, so the building grows as services develop.


  2. Design the operating area for its site. Aircraft dimensions, loading, downwash, charging and emergency access decide what a site can take. Proximity to the main terminal helps transfers, but it is one factor alongside aircraft operations and safeguarding surfaces.


  3. Safeguard space for more pads, stands and charging, with approach surfaces and duct routes protected from day one.


  4. Assess shared services. Rescue and firefighting, security and car parks can be shared only where their suitability and capacity have been checked.


Commercial routes are getting closer, but remain conditional. Vertical, Skyports and Bristow plan a first phase of UK services from Q1 2029, subject to regulatory approval and to Vertical's Valo aircraft gaining CAA and EASA certification. A modular masterplan lets an airport safeguard land now and build only when an operator commits.


Data centres bring a different kind of uncertainty: not when the rules will settle, but when tenants and power will arrive.


Data Centres: Capacity Built In Blocks



Data centres are already modular by nature. Capacity is often added hall by hall and plant block by plant block, which suits an airport estate released in phases. Airports use the approach for their own systems: in 2017 Dubai Airports awarded a contract for mirrored modular Tier III facilities to support its critical operations, and Melbourne Airport has contracted a prefabricated edge data centre that will support critical ICT infrastructure as part of its development plan.


Commercial campuses on airport land are a larger opportunity. Developers are looking at land around airports, such as the Manor Farm site near Heathrow, and on airport estates. Blackpool shows a modular, phased version. The council has selected Hochtief as preferred concessionaire for a £250m first phase of its Silicon Sands campus beside the airport: a 6MW data centre with planning permission, forming part of a wider masterplan. To release the site, old hangars and administration buildings are being relocated and rebuilt nearer the main runway.


Three design lessons follow:


  • Let capacity follow tenants and power. An existing airport grid connection does not mean spare capacity is available, and research by Roadnight Taylor puts data centre grid connections at three to eight years. Apply early and add halls as power is confirmed.


  • Design each block for a defined range. Rack density and cooling shape floor loading, plant space and electrical distribution, so each hall needs an agreed allowance for change.


  • Check safeguarding early. Building heights, cranes, rooftop plant, plumes and radio interference all need testing against approach surfaces and navigation aids.


As ADP Consulting puts it, the next phase of airport development may be driven by power and data. That is why the shared corridor, substation land and energy planning described earlier matter so much.


Designing For The Airport You Can't Yet See


Regional airports don't need to bet on which future arrives first. Modularisation lets them build what is needed today, safeguard what may come next and add it with reduced disruption, whether that is a terminal bay, an eVTOL pad, a data hall or an opportunity no one has yet proposed.


At GeblerTooth Architects we help airport owners and investors turn that uncertainty into a phased, buildable plan. If you are weighing up vertiports, data centres or expansion on your estate, we'd be glad to talk.