top of page
  • Writer's pictureGebler Tooth Architects

Project Update - Gulfstream - Farnborough

Our site team continue to work hard alongside #Volkerfitzpatrick to assist in the delivery of this exciting new purpose-built 220,000sqft maintenance, repair and operations facility at Farnborough Airport for Gulfstream.


Despite the relentless weather on site over the last few months which has brought many challenges with it, progress is going remarkably well and on program. The entire building envelope is now weathertight, enabling the progression of the ongoing internal fitout works. A recent project milestone was reached with the completion of the main hangar slab covering an area of 107,000sqft.




With project completion due in June 2020 it will serve as Gulfstream’s main resource for customers in the London area, Europe’s busiest business aviation hub and will be amongst the most advanced and sustainable hangar buildings in Europe.



164 views
bottom of page